Nanai Soi 2 Hotel Re-Roof: Reinforced Structure, Waterproof Performance

PROJECTS

Guy Choobal

8/18/2025

Patong Hotel Roof Renovation (Nanai Soi 2) — Zero-Downtime Execution

Project owner: Newly acquired boutique hotel (Patong, Phuket)
Contractor: Thaim To Build
Scope: Full roof strip-and-rebuild with structural reinforcement, thermal/acoustic upgrade, and oversized drainage

Executive Summary

We delivered a turnkey roof renovation in the heart of Patong’s Nanai Soi 2 with zero interior water ingress and no business interruption. Our team sequenced demolition section-by-section, immediately covering each live area with canvas tarpaulins to mitigate rain risk. We rebuilt the roof on reinforced galvanized anti-rust beams and purlins, then installed a high-performance layered system—PE foam, OSB board, asphalt sheet, waterproof membrane, and asphalt shingles—and finished with oversized gutters per the client’s request. Outcome: a cooler, quieter, leak-free property with extended service life.

Project Snapshot

  • Location: Nanai Soi 2, Patong, Phuket

  • Building Type: Multi-storey hotel, operating during works

  • Deliverables: Structural upgrade, roof build-up, waterproofing, thermal/acoustic improvement, drainage upsize

  • HSE & QA: Rain contingency, daily checklists, photo logs, water testing before handover

  • Stakeholder Comms: English/Thai daily updates; issue logs closed out same day

Methodology & Risk Controls

  • Phased Demolition: Carefully removed legacy roofing in small zones to keep the hotel watertight at all times.

  • Live-Area Protection: Immediate canvas/tarpaulin cover-ups and sealed laps to prevent rain penetration.

  • Structural Reinforcement: Installed galvanized anti-corrosion beams and purlins to current best practice.

  • Precision Build-Up:

    1. PE foam for thermal and acoustic comfort

    2. OSB board for a rigid, even substrate

    3. Asphalt sheet and waterproof membrane for redundancy

    4. Asphalt shingles for durability and aesthetics

  • Drainage Optimization: Large-capacity gutters and downpipes to manage Patong’s heavy storm events.

  • Quality Assurance: Fastener schedules, membrane overlap checks, line-and-level verification, and controlled water tests.

Materials & Systems (Key Highlights)

  • Structure: Hot-dip galvanized steel beams & purlins (anti-rust; low maintenance)

  • Insulation: Closed-cell PE foam to cut heat gain and reduce rain noise

  • Deck/Substrate: OSB board for uniform load distribution and shingle performance

  • Waterproofing Stack: Bituminous asphalt sheet + membrane for dual protection

  • Finish: Asphalt shingles—weather-resilient and serviceable

  • Drainage: Oversized gutters tailored to roof area and rainfall intensity

Why Thaim To Build

  • Operational discipline: Phased sequencing and watertight workfronts.

  • Craftsmanship: Clean detailing at valleys, ridges, and penetrations.

  • Accountability: Transparent daily reporting, bilingual site leadership, and safety-first culture.