Nanai Soi 2 Hotel Re-Roof: Reinforced Structure, Waterproof Performance

PROJECTS

Guy Choobal

8/18/2025

Patong Hotel Roof Renovation (Nanai Soi 2) — Zero-Downtime Execution

Project owner: Newly acquired boutique hotel (Patong, Phuket)
Contractor: Thaim To Build
Scope: Full roof strip-and-rebuild with structural reinforcement, thermal/acoustic upgrade, and oversized drainage

Executive Summary

We delivered a turnkey roof renovation in the heart of Patong’s Nanai Soi 2 with zero interior water ingress and no business interruption. Our team sequenced demolition section-by-section, immediately covering each live area with canvas tarpaulins to mitigate rain risk. We rebuilt the roof on reinforced galvanized anti-rust beams and purlins, then installed a high-performance layered system—PE foam, OSB board, asphalt sheet, waterproof membrane, and asphalt shingles—and finished with oversized gutters per the client’s request. Outcome: a cooler, quieter, leak-free property with extended service life.

Project Snapshot

  • Location: Nanai Soi 2, Patong, Phuket

  • Building Type: Multi-storey hotel, operating during works

  • Deliverables: Structural upgrade, roof build-up, waterproofing, thermal/acoustic improvement, drainage upsize

  • HSE & QA: Rain contingency, daily checklists, photo logs, water testing before handover

  • Stakeholder Comms: English/Thai daily updates; issue logs closed out same day

Methodology & Risk Controls

  • Phased Demolition: Carefully removed legacy roofing in small zones to keep the hotel watertight at all times.

  • Live-Area Protection: Immediate canvas/tarpaulin cover-ups and sealed laps to prevent rain penetration.

  • Structural Reinforcement: Installed galvanized anti-corrosion beams and purlins to current best practice.

  • Precision Build-Up:

    1. PE foam for thermal and acoustic comfort

    2. OSB board for a rigid, even substrate

    3. Asphalt sheet and waterproof membrane for redundancy

    4. Asphalt shingles for durability and aesthetics

  • Drainage Optimization: Large-capacity gutters and downpipes to manage Patong’s heavy storm events.

  • Quality Assurance: Fastener schedules, membrane overlap checks, line-and-level verification, and controlled water tests.

Materials & Systems (Key Highlights)

  • Structure: Hot-dip galvanized steel beams & purlins (anti-rust; low maintenance)

  • Insulation: Closed-cell PE foam to cut heat gain and reduce rain noise

  • Deck/Substrate: OSB board for uniform load distribution and shingle performance

  • Waterproofing Stack: Bituminous asphalt sheet + membrane for dual protection

  • Finish: Asphalt shingles—weather-resilient and serviceable

  • Drainage: Oversized gutters tailored to roof area and rainfall intensity

Why Thaim To Build

  • Operational discipline: Phased sequencing and watertight workfronts.

  • Craftsmanship: Clean detailing at valleys, ridges, and penetrations.

  • Accountability: Transparent daily reporting, bilingual site leadership, and safety-first culture.

green trees near body of water during daytime
THAIM TO BUILD CO.,LTD.

Expert construction and project management solutions provided for Phuket, Koh Phangan and Koh Samui.

Contact

About

projects@thaimtobuild.com

(+66) 89 724 6744

© 2025. All rights reserved.